: Colorado Construction LawCourt Of Appeals Gives Lengthy Analysis Of Changed-Conditions Claims
By Timothy Gordon
URS Group, Inc. v. Tetra Tech FW, Inc. (Colo. App. 2008)
The Colorado Court of Appeals addresses in detail the elements of, and defenses against, a Type-I differing site conditions claim.
URS was the winning remediation subcontractor for a U.S. Army cleanup project managed by Tetra Tech FW, Inc. (TTFW). After beginning demolition, URS encountered problems removing the foundations, and claimed that the conditions encountered were not as represented in the request for proposal. So URS submitted a contract change notification, seeking $9,166.925 in additional costs. TTFW rejected the claim, and URS sued.
Following a bench trial, the trial court found in favor of TTFW on URS's differing site conditions claim, reasoning that URS's recovery was barred by the fact that URS entered into a fixed price contract. The trial court did, however, award URS some damages on other claims. URS appealed the trial court's denial of its differing site conditions claim, and the Court of Appeals reversed. Under the parties' subcontract and applicable government contracting law, in order to recover on a Type-I differing site conditions claim, a contractor must prove that:
the conditions indicated in the contract differ materially from those actually encountered during performance; the conditions actually encountered were reasonably unforeseeable based on all information available to the contractor at the time of bidding; the contractor reasonably relied on its interpretation of the contract and contract-related documents; and the contractor was damaged as a result of the material variation between expected and encountered conditions.
The Court of Appeals analyzed and rejected TTFW's assumption-of-risk argument, and TTFW's argument that URS should have reviewed certain drawings not referenced in the request for proposal prior to submitting its bid.
Additionally, the Court of Appeals addressed, but could not resolve, TTFW's argument that URS's claim should be barred for failure to provide timely notice of its claim. Because the issue of notice would require a remand and findings by the trial court, the Court of Appeals set forth some of the applicable standards with respect to proper notice, including: the purpose of giving timely notice; the proposition that notice need not be given again for the same recurring issue; the proposition that the notice requirement can be waived if the government had actual or constructive notice; and the proposition that a claim can only be barred if the lack of notice prejudiced the government.
Finally, the Court of Appeals held that URS could maintain a claim for negligent misrepresentation based on the allegedly incorrect bidding information in the request for proposal, and that the economic loss rule would not bar such a claim since it is based on pre-contract conduct.
This opinion should be read in conjunction with the Court of Appeals' decision in Specialized Grading v. Goodland (Colo. App. 2007), wherein the Court held that a subcontractor can maintain a quantum meruit claim against the general contractor based on the general contractor's failure to have the site ready as promised.
Full post as published by Colorado Construction Law on February 07, 2008 (boomark / email).
Selection of State Supreme Court Judges
How State Court Judges are Selected
Law Enforcement and Criminal Justice Career Choices
Descriptions of law enforcement occupations
Paxil Lawsuit
Paxil Claims, Lawsuits, and Injuries
California Supreme Court Proposition 8 Decision
Court Rejects Challenges to Proposition 8, but Finds Marriages Valid
Is Barack Obama a Natural Born Citizen?
Wrotnowski v. Bysiewicz (Supreme Court): Does Obama meet the constitutional requirements to be President
Heart of Atlanta v United States
Supreme Court Decision: Civil Rights Act Protected by Interstate Commerce Clause
Personal Injury
Appeals Court Upholds Congressional Legislation
Pre-Existing Conditions
Insurance companies to pay over $2.1 million settlement in claims lawsuit.
Oil and Gas
industry workers allegedly subject to serious accident injury from hazardous conditions.
False Claims
Attorney Robert Arledge ordered to pay $5.8 million after making false Fen Phen settlement claims.
LINA - Cigna Life Insurance Company of North America Disability Claims
LINA Insurance alleging violations of disability insurance claims.
Ebay Fined
French Court Sets Fine at $61 Million

Antitrust, Single Entities, and the NFL
Ind. Decisions - "Appeals court says Kalab's siblings' records should not have been released"
Ind. Decisions - "Court of Appeals orders Democrat be sworn in as 4th Ward representative"
"Expert who changed mind claims immunity, but plaintiffs still sue"
German Court of Appeals Allows Suit by Claims Consolidator to Go Forward
Contractor Prevails on Differing Site Condition and Notice Issue in Colorado