Home -> Law Blog Directory -> Construction Law Blogs -> The South Carolina Construction Law Blog
(866) 635-2689 for Personal Injury or (866) 635-9402 for Criminal Defense
Find a Local Lawyer
Divorce (866) 635-6190
Personal Injury (866) 635-2689
Criminal Defense (866) 635-9402
Construction Law
: The South Carolina Construction Law BlogConcurrent Delay Damages, Award and Allocation
By Ryan McCabe
Michael and Daniel Drewry discussed the downstream allocation of concurrent delay damages in the
If delays occur around the same time, courts will usually find they are concurrent. The party seeking damages has the burden to prove the delay is not concurrent. If the court decides the delays are concurrent, it will not be able to separate them and will likely not award damages.
Courts have usually taken three approaches in attributing concurrent delays. First, if the delays cannot be separated, neither party is entitled to seek damages. The second approach is to apportion damages based on comparative fault. Third, the critical path method (CPM), identifies delays that are critical to the project and allocates them to the responsible parties.
Defining concurrency is critical to identifying concurrent delays. Concurrent delays do not have to be simultaneous; they can be chronological. Thus, delays may occur at different times, but be related by circumstances. The time range can vary from days to several weeks. In addition, some jurisdictions only consider delays concurrent if they are critical to the project.
Delays should be traced and attributed to responsible parties. Isolate and assign damages that are non-excusable and compensable while keeping contract terms in consideration. The apportionment does not have to be exact. A contractor may apportion an entire concurrent delay to a subcontractor who is responsible for a substantial portion of it. The apportionment is a fact-based issue for the jury. It is important, therefore, to keep as much project documentation and information as possible.
In trying to apportion concurrent delays, a claimant may face several defenses. The difficulty of apportioning concurrent delays is a defense in itself. If delays cannot be apportioned, the remedy is usually just time extension. Even if delays can be apportioned, the claimant may not be able to convince the court the allocation among the responsible parties is adequate. A subcontractor may also claim that it was pacing its work: the predecessor was causing delay and the subcontractor was simply timing its work in the face of the preceding delay. However, a subcontractor who uses the pacing defense faces the risk of being accused of concurrently delaying the overall project if the subcontractor could have made up for the predecessor?s delay by reasonably accelerating its work.
Another defense to an accusation of concurrent delay is that the responsible party, while causing delay, was consuming float time. Float is the difference between the earliest and the latest expected time for a particular activity; it is the extra time to complete the activity without delay liability. Notice is another defense. A claimant must give notice to the responsible party within 21 days of incurring cost or learning of the conditions that give rise to a claim.
The existing law permits allocation of concurrent delays among responsible parties; the difficulty is doing so successfully.
This site and any information contained herein is intended for informational purposes only and should not be construed as legal advice. Seek a competent attorney for advice on any legal matter.
Full post as published by The South Carolina Construction Law Blog on January 28, 2009 (boomark / email).
Bextra Injury Risks
Bextra Increases Risk of Fatal Heart Attack
Medical Malpractice Suits Brings $37M Award
Medical Malpractice Suits Brings $37M Award
Asbestos Mesothelioma Lawsuit Brings $4.5 Million Award
Asbestos Mesothelioma Lawsuit Brings $4.5 Million Award
Environment Law
alleging damages from violation of the law.
Skilled Health Care Faces $670 Million in Damages over Nursing Home Violations
Skilled Health Care Faces $670 Million in Damages over Nursing Home Violations
Failure-to-accommodate claim yields $1.82M award
$1.82 Million Awarded in Employment Lawsuit
Ministry of Defense
$500,000 in damages in transgender humiliation suit.

Allocation of Concurrent Delay Damages on Construction Projects
Anti-Concurrent Cause Exclusion Blows.
Allocation and cumulative need









