: Construction Law BlogGovernment Contractor Collects Consultant’s Fees incurred in Preparing a Request for Equitable Adjustment
By John P. Ahlers
In government contracting, claim preparation costs (attorneys' fees and consultant costs) are generally not recoverable by the contractor when pursuing a claim. On the other hand, if consultant costs are incurred in preparing a "request for equitable adjustment," the consultant costs and attorneys' fees may be recoverable. It depends on the somewhat nebulous distinction between an administrative cost and a cost incurred incident to prosecution of a contract claim. As long as the consulting costs and attorneys' fees are incurred in the preparing of a request for equitable adjustment, for the purpose of seeking a negotiated resolution of pending issues, the costs are allowable. If the contractors' "genuine purpose" in incurring the costs was to further the negotiation process, it is a contract administrative cost allowable under FAR 31.205‑33. On the other hand, however, if the underlying purpose was to promote the prosecution of a Contract Disputes Act (CDA) claim, the costs are not allowable. Under FAR 31.205‑33(b), the cost of legal and consulting services are generally allowable "when reasonable in relation to the service rendered." "A cost is reasonable if, in its nature and amount, it does not exceed that which would be incurred by a prudent person in the conduct of competitive business." FAR 31.201‑3.
The Board held that the contractor was entitled to the consulting costs incurred in preparing the request for equitable adjustment, but because the consultant's work had not been monitored and because the consultant's services were categorized under generalized terms such as "schedule analysis," "developing issue files," "summarized findings/developed schedule REA" and "finalized REA," the Board determined it was not possible to discern the level of detail of work that was actually being performed by any given person on a given day and therefore, reduced the contractor's costs.
Government contractors, when faced with whether to present a request for equitable adjustment or file a certified claim, should weigh the recovery of claim preparation costs, but non‑recovery of interest in a request for equitable adjustment presentation vs. making a claim pursuant to which interest is recoverable under the CDA, but claim preparation costs are not. To prevail, however, on the request for equitable adjustment, the contractor's burden is to show that the "genuine purpose" in incurring the attorneys' fees and costs was to further the negotiation process rather than to simply disguise a claim. Find the case here
Full post as published by Construction Law Blog on April 06, 2008 (boomark / email).
The Paulson Toxic Mortgage Debt Security Act: The Biggest Government Bailout of All Time
Legislative Proprosal for Treasury Authority to Purchase Mortgage-related Assets
Cell Phone Early Termination Fees
How to recover billing errors
Government Overbilling
Defense contractor to pay $8.9 million settlement in fraud lawsuit.
Qui Tam Whistleblower - Government Fraud - Qui Tam Lawsuit
Qui Tam Whistleblower alleging fraud against the government reported by an individual acting as a government whistleblower.
Excessive Bank Overdraft Fees
Bank Overdraft Fees alleging excessive fees and misrepresentation of account balances and more.
Canadian Government
seeks new law enabling them to search your laptop
Federal Government
alleging discrimination against black farmers
US Government
alleging land surveyors should not be allowed on private property to build a US Mexican border wall.

Equal Access to Justice Act Attorney's Fees Denied to a Prevailing Party
Attorney's Fees and Construction Contracts
Legal owner responsible for timely payment of maintenance fees, equitable owner out of luck
Supporting the Right to Obtain a Disability Carrier's Underwriting Manuals
Libertarians Supporting More Governmental Regulation